Power out, sparks or a burning smell?

Emergency WhatsApp
Circuit Dubai electrician logo: a lightning bolt on a navy shieldCircuit Dubai
Inspection, testing and safety

Electrical Design, Single Line Diagrams, Load Calculations, BOQ and Estimating in Dubai: Electrical Engineer Services

Every electrical installation starts as numbers and drawings. Someone adds up the load, decides how big the supply and the main breaker must be, draws how the boards and circuits connect, lists what must be bought and installed, and puts a price on it. When that work is done well, the installation goes in once. When it is skipped, the cables, the breakers and the board are sized by guesswork, and the quote is a guess too.

Circuit Dubai prepares the electrical side of that work for villas, apartment buildings, offices, shops, warehouses and small industrial units across Dubai: load calculations, single line diagrams, distribution board schedules, layout drawings, bills of quantities and cost estimates, and reviews of existing designs. We are electricians who install what we design, so the drawing is checked against how the job is built. Drawings that must be submitted for approval carry the signature of a registered consultancy, and this page says plainly where our work stops and theirs starts.

Electrical components laid flat: MCBs, RCD, clamp meter, ammeter and coloured wires, electrical design services and load calculation for Dubai

What electrical design with us includes

The load worked out first, from the equipment list and the plans, so the supply, the main breaker and the cables are sized from numbers and not from habit.

A single line diagram that matches the build, showing the supply, the boards, the breakers and the cables with their ratings.

Schedules and layouts, with a board schedule for every distribution board and a layout showing where each point, circuit and board sits.

A bill of quantities, so every installer prices the same list and quotes can be compared line by line.

A cost estimate with its parts shown, so you can see what drives the price before any work starts.

A clear boundary on approvals, so you know which drawings we issue and which go through a registered consultancy to the authority.

The numbers at a glance

Typical answer for Dubai

What we doLoad calculation, single line diagram, board schedules, layout drawings, BOQ, cost estimate and design review
PropertiesVillas, apartment buildings, offices, shops, warehouses and small industrial units
Supply basisSingle-phase 230 V or three-phase 400 V at 50 Hz
What we need to startArchitect plans, the equipment list, the supply you have or expect and the stage the project is at
OutputDrawings and schedules as PDF, plus editable files where agreed
ApprovalsDrawings for submission are signed by a registered consultancy
Site visitFor an existing building, a visit to check the board, the cables and the loads before drawing. The visit costs AED 50.
PriceFixed per package after we see the plans

Before you book electrical design work, send the architect's plans if you have them, in PDF or CAD. List the big loads you know about: air conditioning units and their tonnage, water heaters, a pool, a lift, kitchen equipment, an EV charger, a workshop machine. Say what stage the project is at, whether it is a new build, a fit-out or an existing building, and what supply the building has or expects. If you already have an electrical drawing or a BOQ from someone else, send it, because a review is quicker than a new design. That is enough for us to say what you need and what each part costs. The sections below explain the work so you can judge any quote or drawing before you accept it.

Terms

Electrical engineering terms: what people search for and what each means

People search this subject in many ways. Some searches are for a service, some are for a job or a degree, and some are fragments with no clear meaning. The tables below say which is which, so you land on the part of this page that fits, and so we do not pretend to answer a search we cannot.

Engineer and consultant terms

If you searchedWhat it means
Electrical engineer, an electrical engineer, electrical engineer doA person who designs, calculates and specifies electrical systems. See the electrical engineer section for what that means on a building job
Electrical engineer near me, electrical design engineer near meSomeone local who can design or check an installation. Our office is in Al Quoz and we work across Dubai
Senior electrical engineer, sr electrical engineer, lead electrical engineer, principal electrical engineer, chief electrical engineerJob titles that show seniority in an engineering firm. They describe a position and not a service. See the electrical engineer section
Junior electrical engineer, associate electrical engineer, graduate electrical engineer, trainee electrical engineerEntry level job titles. See the electrical engineer section
Mep electrical engineer, electrical engineering mepThe electrical side of mechanical, electrical and plumbing design on a building. See the design stages section
Bim electrical engineerAn electrical engineer who models the installation in building information modelling software. See the drawings section
Licensed electrical engineer, professional electrical engineer, chartered electrical engineerTitles tied to registration with an authority or a professional body, and they differ by country. See the rules section
Freelance electrical engineerAn engineer who works for clients on their own account. See the consultancy section
Electrical consultant, electrical consultant engineer, electrical consultant company, electrical consultancy services, electrical engineering consultant, electrical engineering consultants near me, electrical engineering consultancy servicesA firm or person that designs and advises and does not install. See the rules section and the consultancy section
Forensic electrical engineerAn engineer who investigates why an electrical system failed. See the forensic section
Electrician to electrical engineerA career question about moving from installing to designing. See the electrical engineer section

Drawing, BOQ and estimating terms

If you searchedWhat it means
Single line, electrical single line, single line circuitA single line diagram, the one drawing that shows how the supply, boards and breakers connect. See the single line diagram section
Electrical engineering draftingProducing the drawings of an installation. See the drawings section
Boq electrical, boq electrical work, boq for electrical work, boq in electrical, boq of electrical works, electrical work boq, electrical boqA bill of quantities for electrical work. See the BOQ section
Electrical bill of quantities, electrical bill of quantities example, electrical boq sample, sample boq for electrical work, electrical boq format, boq for electrical work xlsWhat a BOQ looks like and how it is laid out. See the BOQ section for a sample layout
Electrical boq for residential building, sample electrical boq for residential house, electrical boq for commercial buildingA BOQ for a house or a commercial building. See the BOQ section
Electrical boq with ratesA BOQ with a price against each line. See the BOQ and the cost sections
Electrical estimate example, electrical estimate for house, residential electrical estimatingA worked cost estimate for a home. See the estimating section
Electrical estimating service, electrical estimating services, electrical estimation, estimating electrical work, estimation in electrical engineering, cost and estimation in electrical engineeringWorking out what an installation will cost from the drawings. See the estimating section
Electrical installation estimating, electrical installation and estimating, electrical installation estimating and costing, electrical installation estimating & costingThe same work, with the costing step. See the estimating section

Searches that are not a service

These are searches for jobs, study, companies elsewhere or topics we do not offer. We say so here so you are not left guessing.

If you searchedWhat it means
Electrical engineering degrees, bsee electrical engineering, be electrical engineering, me electrical engineering, ee electrical engineering, eit electrical engineeringStudy and qualification searches. BSEE is a bachelor of science in electrical engineering, BE and ME are bachelor and master of engineering degrees in some countries, and EIT is a US engineer in training title. We do not teach or certify
Electrical engineering is hard, electrical engineering technician, trade test certificate electrical engineeringQuestions about study difficulty and technician or trade qualifications. We do not issue qualifications, and the authority that licenses electrical workers in Dubai sets its own requirements
Electrical engineering and computer science, electrical engineering & computer science, electrical engineering science, electrical engineering information, electrical engineering websites, electrical engineering springer, russian electrical engineeringAcademic subjects, publishers and journals. This page is about the electrical design of buildings
Auburn electrical engineering, iisc electrical engineering, nptel electrical engineering, sait electrical engineering, electrical engineering waterlooThe electrical engineering departments or course platforms of institutions in other countries. We have no connection to them
Apple electrical engineer, google electrical engineer, microsoft electrical engineer, nasa electrical engineer, aerospace electrical engineer, r&d electrical engineerJobs at named employers, in aerospace and in research. This page covers building electrical design
Indeed electrical engineer, gaji electrical engineer, highest paid electrical engineer, bls electrical engineerJob listings and pay data. Gaji is the Malay and Indonesian word for salary. We do not publish pay data or job listings
Arc electrical engineering pte ltd, sing moh electrical engineering pte ltd, green power electrical engineering consultants, cwc electrical engineering serviceCompany names. Pte Ltd is a private company form used in Singapore. We are not connected to any of them
P1 and p2 electrical engineering, prc electrical engineering, r electrical engineering, in electrical engineeringFragments we cannot place. They read like course codes, abbreviations or part of a longer phrase. If you meant something specific, send it to us on WhatsApp
Civil electrical engineering, electrical engineering and mechanical engineering, mechanical and electrical engineering, mechanical and electrical engineering combined, mechatronics electronic control systems in mechanical and electrical engineeringBroad subject names. The building side is covered in the design stages section, and machine control is covered on our motor and lift wiring page
Electrical engineering materials, electrical engineering power systems, industrial electrical engineering, control systems electrical engineeringSubject areas. See the power systems and industrial section for how they apply to a building
Electrical engineering companies, electrical engineering companies near me, top electrical engineering companies, electrical engineering firms, electrical engineering firms near me, electrical engineering contractor, electrical engineering contractors, electrical engineering services, electrical engineering workA search for a firm to hire. See the consultancy section for how to compare them, and for what we are
Planning

How electrical design is planned: what to decide before drawing anything

Electrical design decisions are easiest to make before the walls are built. The decisions below are made once, in this order, because each one changes the next.

The questions that decide the design

QuestionWhy it decides the design
What is the building and who will use it?A villa, an office, a restaurant kitchen and a workshop load a supply very differently
What are the big loads?Air conditioning, water heating, a pool, a lift, kitchen equipment and EV charging are each large enough to change the size of the supply
What supply is available?The size and type of supply set the main breaker and the cable from the meter
Is there room to grow?Spare ways and spare capacity are added at design stage by the choice of board, and later by a new board or a new supply
Will anything run on backup?A generator, a UPS or a battery changes the board layout and the single line diagram
What will the authority need to see?Approval drawings follow a set format and need a registered signature
Who installs it?A design that the installer cannot read or build costs money on site

Who does what on a design job

ItemWho does it
Building plans and layoutThe architect
Electrical load calculation, single line diagram and design that is submitted for approvalA registered consultancy, with our input where we are on the job
Load calculation, single line diagram, schedules, layouts and BOQ for pricing, review or a small jobUs
Submission to the authority and its approvalThe registered consultancy or the contractor the authority accepts
Installation and testing to the approved drawingsUs, with licensed workers
Record drawings after the jobUs

Design for what already exists

A job is not always a new build. A villa that is adding a pool, a floor, a kitchen or EV charging, or an office that is changing its layout, needs the existing installation measured before anything is added. We visit, read the board, record the breaker ratings, the cable sizes where they can be seen and the measured loads, and then draw what is there and what is proposed. If the main supply cannot take the new load, see our three-phase and load upgrade page. If the board is full or old, see our DB box and distribution board page.

Rules

Rules for electrical design in Dubai: who may design, who may submit and what is checked

Electrical design in Dubai sits under the wiring regulations, the building code, the engineering consultancy rules and the supply authority's approval process. We are electricians and not lawyers, so confirm what applies to your project with your consultant or the authority.

What applies and where it comes from

SubjectWhat applies
Engineering consultancyA law firm's published summary says Dubai Law 14 of 2025 regulates engineering consultancy in Dubai, covers electrical engineering among other disciplines, and bars anyone from practising or advertising as a consultancy without a trade licence and a registration kept by Dubai Municipality. It gives existing offices until April 2027 to regularise. This page relies on that summary and not on the law's own text.
Design that is submitted for approvalSigned by a registered consultancy, which is also the one that submits it. Our design information supports that work and does not replace it
Supply authorityDEWA publishes Regulations for Electrical Installations and runs the approval, inspection and connection process. This page does not repeat DEWA's clause numbers, and we work to the edition in force for your project.
Building permitsDubai Municipality runs the building permit process. Its site says it has accredited consultancy offices to submit self-build villa permit applications for Emirati citizens, and that the consultant checks compliance with the Dubai Building Code.
Standards for the installationIEC 60364 covers the electrical installations of buildings, and IEC 61439 covers low-voltage switchgear assemblies such as distribution boards. Which editions the authority accepts is
Fire and life safetyFire alarm, emergency lighting and similar systems follow the fire authority's rules. See our fire alarm and smoke detector installation page.
Permission from the landlord or buildingChanges to a building's supply or its risers may need approval from the landlord or the building management.

What the approval route looks like

An independent exam-prep guide for the Dubai electrical licence exam summarises the DEWA process in the stages below. It is a study guide and not DEWA's own text, and it does not say who reviews each step, so treat it as a map to check with DEWA and your consultant.

StageWhat happens
No objection certificatesClearances for the plot, including a Building Electrical NOC that confirms grid capacity, applied for through the unified building permit system or DEWA e-services
Load estimationThe consultant calculates connected load and maximum demand in kVA. The exam-prep guide gives 400 kVA as the point above which a building must provide room for a substation, and that figure is
Drawing submissionA consultant or a certified contractor submits the single line diagrams, schedule of loads, layouts and earthing drawings
Installation and testingThe contractor installs to the approved drawings and tests before asking for inspection
InspectionThe contractor books the inspection and uploads test sheets and as-built drawings. The inspector checks that what is installed matches what was approved
Clearance and energisationDEWA issues clearance, installs the meter and energises the supply

The point that matters for design is the last line of the inspection stage. What is installed must match what was approved, so a design that cannot be built as drawn is a problem on inspection day and not only on site.

Engineer

What an electrical engineer does on a building job, and what the job titles mean

An electrical engineer designs and specifies the installation, and an electrician builds and tests it. On a building job the engineer's work is mostly decisions on paper that the electrician later turns into cable, boards and devices. The two jobs overlap on site, where a good engineer walks the job and a good electrician reads the drawings.

What the design work covers

TaskWhat it produces
Take the briefA list of loads, areas, uses and expected growth
Load calculationConnected load, maximum demand and the current at the supply
Supply and board designThe size of the main breaker, the board layout and the number of ways on each board
Circuit designCable sizes, protection ratings and the checks on voltage drop
Short circuit and protection checksBreaker ratings that can break the fault current at the board
Earthing and lightning designThe earthing arrangement. See our earthing and grounding and lightning protection pages
SpecificationThe makes, ratings and standards of the equipment
Drawings and schedulesSingle line diagram, board schedules and layouts
BOQ and estimateThe quantities to price and the expected cost
Site reviewVisits to check that the build follows the design
Testing and handoverWitnessing the tests and issuing record drawings

What the job titles mean

Firms use titles differently, and there is no single scale across them. The table is a rough guide, and a title tells you less than the work a person has signed.

TitleWhat it points to
Junior electrical engineer, graduate electrical engineer, trainee electrical engineer, associate electrical engineerEarly career, working under a more senior engineer on parts of a design
Electrical engineerCarries out design tasks on a project
Senior electrical engineer, sr electrical engineer, lead electrical engineerResponsible for a design area or a project team
Principal electrical engineer, chief electrical engineerHeads a discipline or a department in a firm
Licensed electrical engineer, professional electrical engineer, chartered electrical engineerA title linked to registration with an authority or a professional body, which differs by country
MEP electrical engineerThe electrical engineer on a mechanical, electrical and plumbing design team
BIM electrical engineerAn engineer who builds the electrical model in building information modelling software
Freelance electrical engineerAn engineer working on their own account. See the consultancy section for what to ask

In Dubai, the registration that matters for signing and submitting design is the one the authority requires of the consultancy and its engineers, as in the rules section.

From electrician to electrical engineer

People who search electrician to electrical engineer are asking about a career move. The jobs are different. An electrician installs, tests and repairs to the drawings. An engineer produces the drawings and takes responsibility for the calculations behind them. The move runs through formal engineering study and, for signing designs, registration with the authority, and what the authority accepts is set by the authority. We do not run training or issue qualifications.

Load calculation

Electrical load calculation: connected load, maximum demand and the size of the supply

The load calculation is the first number in any design, and every size after it depends on it. A supply that is too small trips under load. A supply that is too large costs more in cable, breakers and board space than the building needs.

The load calculation in four steps

1

List every load. Lighting, socket circuits, air conditioning, water heaters, pumps, kitchen equipment, lifts, EV chargers and any machinery, each with its rating.

2

Convert to kVA. A rating in kW is divided by the power factor to give kVA. Add the kVA to get the connected load.

3

Apply diversity. Not everything runs at once, so each group of loads is multiplied by a factor that reflects how much of it runs at the busiest time. The result is the maximum demand.

4

Find the current. For a three-phase 400 V supply, the current is the maximum demand in kVA times 1,000, divided by 1.732 times 400. The main breaker and the cable from the meter are chosen from that current, with room for growth.

Connected load is what is installed, and maximum demand is the most that is drawn at one time over the period measured. Maximum demand is never more than connected load. The ratio of the two is the demand factor.

Diversity: why the factors matter

An installation design guide separates two ideas. The utilisation factor adjusts a load's rating to how much it is really used, and the diversity factor adjusts a group of loads for the fact that they do not all peak together. The guide lists values for distribution board assemblies under IEC 61439-2: 0.9 for 2 to 3 circuits, 0.8 for 4 to 5, 0.7 for 6 to 9 and 0.6 for 10 or more. It advises values close to 1 for mainly lighting circuits, and for lifts it gives 1 for the most powerful motor, 0.75 for the second and 0.6 for the rest. For an apartment block with 25 consumers of 6 kVA each, in homes without electric heating under a French standard, the same guide gives a factor of 0.46, which turns 150 kVA of installed load into a 69 kVA design demand and a current of about 100 A at the base of the rising main.

Two points apply to Dubai. A cooling load is on for long hours in a Dubai summer, so the example below gives it a factor of 1. And the factors that DEWA accepts are set by DEWA and not by a guide from another country. An exam-prep summary attributes allowances to DEWA's regulations, and we do not use them without checking the current regulations.

A worked maximum demand example

This is an illustration of the method for an imagined villa. The factors are for the example only, and a real design uses the factors that apply to the project. The loads are not a design.

Load groupConnected load (kVA)Factor used hereDemand (kVA)
Lighting3.00.72.1
Socket outlets15.00.46.0
Air conditioning28.01.028.0
Water heaters6.00.84.8
Pool pump and other fixed plant3.01.03.0
Kitchen appliances8.00.54.0
Total63.047.9

The demand factor is 47.9 divided by 63, which is about 0.76. The current at 400 V three-phase is 47,900 divided by 692.8, which is about 69 A. A designer then adds spare capacity for future loads, checks how the single-phase loads are shared across the three phases so that no phase carries far more than the others, and picks the main breaker from standard ratings and the supply authority's requirements.

From load to cable: current, cable size and voltage drop

Once the current is known, each circuit gets a protective device and a cable. The cable must carry the circuit's current in the way it is installed, which means in conduit, on tray, buried or in a hot roof space, because heat and grouping reduce what a cable can carry. It must also keep the voltage drop within the limit the regulations set, which matters on long runs to a pump, a gate or a detached building. And the breaker must be able to break the fault current available at the board, so the breaker's breaking capacity is checked against the fault level.

We show each cable's size, its protective device and its length on the board schedule, so the person who installs it and the inspector who checks it read the same numbers. See our MCB and RCCB breakers page for what each device does. For cable lugs, joints and large cables, see our cable termination and jointing page.

What goes wrong when the load is guessed

  • A full board on day one, with no spare ways, so the next circuit needs a new board.
  • A cable that overheats or drops too much voltage, because the run was longer or hotter than assumed.
  • A main breaker that trips in summer, because air conditioning was given diversity it does not have.
  • A phase that carries most of the load, because the single-phase circuits were not shared across the three.
  • A supply request that is too small or too large, which is a delay at the authority or a cost for capacity that is not needed.

If your concern is the running cost and efficiency of the installation after it is built, see our energy audit page. If the power factor of the supply is the issue, see our power factor correction page.

Single line diagram

Single line diagram: how to draw and read an electrical single line

A single line diagram, also called a one-line diagram, shows an installation on one page with one line standing for the three phases. Searches for single line, electrical single line and single line circuit all point to this drawing. It is the one drawing that lets an engineer, an installer, an inspector and the authority read the same system.

What a single line diagram shows

A single line diagram is a simplified symbolic drawing of how power flows from the source to the loads. A design explainer lists what it normally carries.

ElementWhat is shown
Source and voltageThe utility supply, a generator, a UPS or an inverter, and the voltage levels
TransformersThe kVA rating, the voltage ratio and the connection, where there is one
Boards and busesThe main and sub-distribution boards with their current ratings
Protection and switchingBreakers, fuses, isolators and changeover switches with their ratings
MeteringMeters and current transformers where used
FeedersThe cable size and type between boards and the equipment each supplies
TagsEquipment names that match the schedules and other drawings

The symbols differ between standards and projects, so the legend on the drawing decides what each one means.

How to read one in two passes

1

Trace the path. Read the title block, the revision and the legend. Find every source. Follow the supply through each board to each load, and note where the voltage changes. Say aloud what the normal path is and what the alternate path is, if there is one.

2

Read the data. Go back over each item and note its tag, rating and note. For each note, separate what it states, what you can conclude from it and what still needs checking against a datasheet or a schedule.

An example for a villa

StepWhat is drawn
1The supply from the utility meter
2The main breaker
3The main distribution board
4Feeders from the main board to the sub-boards, such as the first floor, the pool plant and the outdoor board
5The final circuits on each board, labelled and rated, grouped as lighting, sockets, air conditioning and fixed equipment
6A generator or a UPS with its changeover, where fitted. See our generator installation and servicing and UPS and inverter installation pages

What it does not show

A single line diagram does not show the physical wiring between terminals, the route of cables, the layout of a panel or the present position of a switch in the field. It does not show whether a circuit is dead or safe to touch. It does not show protection settings, the fault current available or whether the installation complies, unless that data is recorded on it. Undocumented changes made on site are not on it either.

Stop and keep clear of a board or a circuit because a drawing says it is dead or isolated. A drawing is not an isolation procedure, and it can be out of date. Isolate at the supply, lock off, and prove dead with a tested meter before anyone touches a conductor.

Drawings

Electrical drawings, schedules and the design stages: MEP, BIM and drafting

The single line diagram is one drawing in a set. The set is built in stages, and each stage adds detail to what came before.

The design stages

A design article describes five stages for mechanical, electrical and plumbing design. Electrical engineering MEP work follows the same sequence.

StageWhat is producedElectrical content
ConceptBasic requirements and early modelsLoads estimated at a high level
SchematicPreliminary layouts, diagrams and calculationsRoutes sketched and load calculations assessed against the objectives and the rules
Design developmentTechnical drawings, specifications and selected equipmentTransformers, boards and fittings selected and checked against the code
Construction documentsThe coordinated drawing set and schedulesLayouts, board schedules and quantities
Construction supportAnswers to queries and review of shop drawingsChecks that equipment and changes still suit the design

A small villa job does not need five formal stages. The same thinking applies, compressed into a visit, a calculation, a set of drawings and a review during the build.

The drawings and schedules in a set

DocumentWhat it shows
Single line diagramHow the supply, boards and breakers connect
Load scheduleThe loads, their ratings and the maximum demand
Board schedulesEvery circuit on each board, with breaker, cable, load and phase
Lighting layoutThe position of each light and switch and the circuits they are on
Power layoutThe sockets and fixed equipment and their circuits
Air conditioning and plant powerThe supply to units, pumps and other plant
Containment layoutThe routes for conduit, trunking and tray
Earthing and lightning layoutThe earth electrodes, bonding and any lightning protection
Low current layoutsData, TV, CCTV, fire alarm and access control, drawn with their own services
Specification and BOQWhat is to be installed and the quantities to price
Record drawingsWhat was actually built, issued after the job

See our conduit, trunking and cable tray page for the containment routes, and our earthing and grounding and lightning protection pages for the earthing layout.

Drawing, drafting and BIM

Electrical engineering drafting is the production of these drawings from the engineer's decisions, in CAD or in a BIM model. A BIM electrical engineer builds the installation as a model in which each board, tray and light is an object with a size and a position. The advantage is coordination, because a model can show a tray clashing with a duct before anyone cuts steel, and quantities can be taken from the model. The cost is set-up time, which a small job may not justify.

For the low current layouts, see our pages on lighting design and control, CCTV installation, TV, data and network cabling and smart home installation, which cover the systems that go on them.

BOQ

Electrical BOQ: bill of quantities format, sample and rates

A bill of quantities, called a BOQ or BoQ, is a list of the items in a design with the measured quantity of each. Searches for electrical boq, boq for electrical work, electrical work boq and electrical bill of quantities all ask for the same document. Its purpose is to make every installer price the same list, so that quotes can be compared line by line instead of as three unrelated totals.

What a BOQ is for

A construction cost reference describes the BOQ this way. It is normally prepared by a cost consultant such as a quantity surveyor, from a finished design and a specification. The items are grouped into work sections that match the packages a subcontractor would price. It says what is to be done and how much, and it leaves the detail of how to the specification.

UseWhat it does
TenderingEach tenderer prices the same quantities, and the priced BOQ becomes the offer
Contract sumThe priced BOQ helps agree the sum with the successful tenderer
VariationsThe rates in the BOQ give a basis for valuing additions and omissions
PaymentsThe items support the valuation of interim payments and the final account

On a large project the BOQ is measured by a cost consultant. On a smaller one, the installer measures from the drawings and a schedule of work, which is why a drawing set with clear schedules saves an installer's time and your money. A BOQ that is approximate, because the design is incomplete, leads to more variations and less certainty on the final price.

A sample electrical BOQ for a villa

This sample shows the layout and the kind of items. The quantities are for an imagined villa and are not from a project. A real BOQ takes its quantities from the drawings. Rates and amounts are filled in when the BOQ is priced. The site visit costs AED 50, and the quote follows it.

RefDescriptionUnitQuantity in this example
ASupply and boards
A1Main distribution board, three-phase, with main breaker, as the single line diagramnr1
A2Sub distribution boards, as the board schedulesnr3
A3Supply cable from the meter position to the main board, size as designedm25
BFinal circuits
B1Lighting points, wired and completenr64
B213 A socket outlet points, wired and completenr58
B3Air conditioning supply points with local isolatornr9
B4Water heater supply points with isolatornr5
B5Cable for final circuits, by size as the board schedulesmby schedule
CContainment
C1Conduit, concealed or surface, by size as the containment layoutmby layout
C2Cable tray and trunking, by sizemby layout
DEarthing
D1Earth electrode with inspection pitnr2
D2Main earth bar and bonding to servicesset1
ETesting and handover
E1Testing and commissioning with test sheetssum1
E2Record drawings and certificatessum1

Each line has one unit and one quantity, and its description points to the drawing or schedule that defines it. That is how a BOQ stays short and exact.

Residential and commercial BOQ

An electrical boq for a residential building is short and repeats the same rooms. An electrical boq for a commercial building has more boards, more containment and more low current services, and can include a generator, emergency lighting and a fire alarm system. It also has more specification clauses, because the equipment is larger and has to coordinate with other trades. See our pages on fire alarm and smoke detector installation and generator installation and servicing for items that appear on commercial BOQs.

BOQ with rates, in a spreadsheet

A boq for electrical work xls is the same list in a spreadsheet, with columns for quantity, rate and amount, and formulas that multiply and total them. An electrical boq with rates fills the rate column. A rate is the price of one unit installed, so it holds the material, the labour, the overheads and the profit for that unit. We deliver the BOQ in an editable file where agreed, so that you can send it to several installers.

The standards for measuring

A BOQ is only as clear as its method of measurement. A cost reference names the UK's SMM7 and NRM, CESMM4 for civil engineering and ICMS as an international standard for reporting costs, and says that using a consistent standard reduces disputes. Which method a Dubai project uses is set by the client and the consultant.

Estimating

Electrical estimating: how an estimate for a house or a building is built

Estimating answers a different question from the BOQ. The BOQ says what and how much, and the estimate says what it will cost. Searches for electrical estimating services, electrical estimation, estimating electrical work and electrical installation estimating and costing all ask for that second answer.

How an estimate is built

A contractor's estimating guide gives the steps below. Our method follows them.

StepWhat it means
TakeoffCount and measure every item from the drawings, sheet by sheet, and keep a total for each sheet
MaterialsPrice each item from current supplier prices. A contractor's guide prices lighting separately as a lump sum from the fixture schedule
LabourHours for each item, from the contractor's own records of past jobs, multiplied by the full hourly cost of the workers
Direct costsMaterials plus labour, plus equipment hire and subcontractors
OverheadA percentage added for the costs of running the business, such as the office, estimating and bookkeeping
ProfitA percentage added on top of direct costs and overhead
PriceDirect costs plus overhead plus profit, given as a lump sum

The contractor's guide gives no percentages for overhead or profit, and neither does this page, because they belong to each business. In the United States, a trade body publishes a manual of labour units for people without records of their own. We use our own records and say so on the estimate.

An electrical estimate for a house

For a residential job, the estimate starts with the BOQ, because the BOQ gives the quantities. Each line is priced with its material and its labour, and the lines are added. A house estimate shows the parts in this order.

PartWhat it covers
Boards and breakersThe main board, sub-boards and the devices in them
WiringLighting, sockets and fixed equipment circuits, by point
Plant suppliesAir conditioning, water heaters, pool and other fixed plant
ContainmentConduit, trunking and tray
Earthing and protectionElectrodes, bonding and surge protection. See our surge protection page
Low currentData, TV, CCTV and other services, if included
Testing and handoverTest sheets, certificates and record drawings
Making goodChasing, plaster and paint where work is in a finished building

Checking an estimate

An estimating guide suggests keeping a log of finished jobs, with the price per unit of floor area, and comparing each new estimate with it. A large difference from past jobs is a reason to look again, and it is not always a mistake. A villa with a pool, a lift and a full backup system will cost more per square metre than a villa without them. We say what drives a difference when we hand over the estimate.

New build and existing building

CaseWhat changes in the estimate
New buildWork in conduit before plaster, on a clear site, with other trades working in the same period
Fit-outExisting services to avoid, a handover date and work that may have to happen outside normal hours
Existing buildingSurveying first, work in a lived-in building, making good and boards that must stay live

What an estimate leaves out

The estimate covers the installation. Fees and deposits that the supply authority charges are separate, and so are the air conditioning units, the light fittings you choose and any building work. We list exclusions on the estimate so you can see what else to budget.

Companies

Electrical engineering companies, consultants and contractors: how to compare them

People who search for electrical engineering companies, electrical engineering firms or electrical engineering contractors are trying to find who should do the work. The terms cover several kinds of business, and the difference matters because it decides who is responsible for what.

The kinds of firm

KindWhat it does
ConsultancyDesigns, specifies, supervises and can submit drawings for approval. Does not install. Registered with the authority
ContractorInstalls, tests and hands over to the drawings. May carry out design for pricing or small jobs
Design and buildOne firm designs and builds under one contract
MEP consultancyDesigns the mechanical, electrical and plumbing services together. Mechanical and electrical engineering consultants and mechanical electrical engineering consultants are the same kind of firm
Freelance engineerAn individual engineer working for clients directly. Check the registration and who submits the drawings

Electrical engineering services and electrical engineering work can be offered by any of these, and the name alone does not tell you which. We are a contractor that prepares design information, and we work with a registered consultancy where a project needs one.

Questions to ask before you hire

  1. 1
    Are you registered, and in which category? Registration in the authority's register is what lets a firm practise and advertise as a consultancy, as the rules section explains.
  2. 2
    Who signs the drawings that go to the authority? The name and the registration should be on them.
  3. 3
    What is in the fee? The load calculation, the single line diagram, the schedules, the layouts and the BOQ should each be on a line.
  4. 4
    How many revisions are included? Plans change, and each change reaches the electrical design.
  5. 5
    Does the fee include site visits and inspection support? Design that is not checked on site drifts from the drawings.
  6. 6
    Who is responsible if the drawing and the site disagree? The answer should be written down.
  7. 7
    What do you hand over at the end? Record drawings, test sheets and an editable copy of the drawings.

A freelance electrical engineer should answer the same questions. A consultant company or electrical consultant engineer that cannot say who signs and submits the drawings has not answered the question that matters.

Rankings of top firms

People search for top electrical engineering companies, and there is no list here. A ranking would need data about quality and cost that we do not hold, so we do not publish one. Compare firms on the questions above, ask to see drawings from a finished job and ask for the contact of a client. For electrical engineering companies near me and electrical engineering consultants near me, the same questions apply, and distance matters for site visits.

Forensic and review

Forensic electrical engineering and design review of an existing installation

When something goes wrong in an installation, two kinds of engineering help. One finds out why it failed. The other checks whether what exists matches what was intended.

What a forensic electrical engineer does

A forensic electrical engineer determines why an electrical system, component or appliance failed. A US forensic engineering firm describes the work this way. The engineer identifies the failure mode, whether it started a fire and whether a defect, an installation error or misuse caused it. The findings support insurance claims and legal cases. The work covers electrical fires, failures of motors, transformers, breakers and control boards, arcing at loose or corroded connections, overloaded circuits and damage from lightning, surges or the supply. The deliverable is a written report that sets out what was examined, the failure mode, the basis for each conclusion and what was ruled out, and the same engineer can give evidence.

We do not act as a forensic expert or give expert evidence. What we can do is carry out the testing and inspection that such an investigation needs, and fix the cause once it is known. See our electrical inspection, thermal imaging inspection, insulation and earth resistance testing and breaker tripping repair pages for the testing and fault finding we do.

Reviewing an existing design or installation

What we checkWhat it tells you
Board loading against the load calculationWhether the supply and the boards have room for what is connected
Cable size against breaker ratingWhether the breaker protects the cable
Earthing and RCD coverageWhether the installation protects people
Voltage drop on long runsWhether equipment at the end of a run is starved
Drawings against the installationWhether anyone can trust the drawings
Spare capacityWhether the next load can be added

The result is a short report with findings ranked by risk and a list of fixes. See our electrical inspection page if you need a formal inspection certificate. See our PAT testing page for portable equipment.

Power systems

Power systems, industrial and control systems: where design meets the rest of the electrical work

Electrical engineering power systems, industrial electrical engineering and control systems electrical engineering are large subjects. For a building, they show up as particular parts of a design, and each has its own page on this site.

SubjectWhere it appears in a building designOur page
Power systemsThe supply, the main board, sub-boards, backup power and power factorGenerator installation and servicing, power factor correction, three-phase and load upgrade
Industrial electrical workMotors, drives, cranes, lifts, panels and PLCsMotor and lift wiring
Control systemsBuilding controls, lighting control, smart home and access controlLighting design and control, smart home installation, access control and intercom
Electrical engineering materialsThe specification: conductor and insulation types, enclosure ratings, devices and containmentThe sections of this page on drawings and BOQ
Green powerSolar, batteries and EV charging, which add generation, storage and large loadsSolar panel installation, battery storage installation, EV charger installation, commercial solar service
Mechanical and electrical coordinationThe equipment ratings from the mechanical side set the load, and the electrical design sizes the supply to suitThe load calculation section of this page

Mechanical and electrical engineering together

A building's mechanical systems carry some of its biggest electrical loads, so the two engineering disciplines work together on a building job. The mechanical engineer states the ratings of the air conditioning, pumps and ventilation, and the electrical engineer sizes the supply, the boards and the cables to suit. A change to a unit on one side reaches the other. We ask for the mechanical equipment schedule at the start of any design, and we update the load calculation when it changes.

Materials in the specification

The specification names what is installed: copper or aluminium conductors, the insulation type, the enclosure rating of boards and the standard each device meets. In a hot, dusty or coastal setting, the enclosure rating and the insulation type are part of the specification, along with the current rating.

Fees

Electrical design, drawing and estimating fees: what affects the price

The price of design depends on how big the building is, how many boards and circuits it has, how complete the information is and how much support you need after the drawings are issued. A quote that gives one figure with no list cannot be compared with one that shows each part.

What goes into the price

FactorWhy it changes the price
Size of the buildingMore area means more circuits, boards and drawing sheets
Number of boards and the supply typeA three-phase supply with several sub-boards takes longer than a single board
Quality of the starting informationClear architect plans and an equipment list save time, and missing information costs time
Existing building or new buildAn existing building needs a survey before any drawing
Items in the packageLoad calculation, single line diagram, schedules, layouts, BOQ and estimate each take their own time
CAD or BIMA BIM model takes longer to set up and adds coordination
RevisionsEach change in the plans reaches the electrical design
ApprovalsSubmission and responses to the authority are separate from drawing
Site supportVisits during the build and witnessing tests

A quote needs the plans, the equipment list and a statement of what you want delivered.

How we price

We give a fixed price per package after we have seen the plans, with the load calculation, the single line diagram, the schedules, the layouts, the BOQ and the estimate on separate lines, so you can buy only what you need. Revisions beyond those agreed are priced when they arise, and we tell you before we start them. If a smaller package does the job, we say so on the quote.

Why us and how to book

Electrical design and estimating with Circuit Dubai

  • Electricians who design, so the drawing is checked against how the job is built and tested.
  • The load worked out from numbers, with the calculation shown and not hidden in a total.
  • A BOQ and an estimate with their parts shown, so a quote can be compared line by line.
  • A clear line on approvals, with what we issue and what a registered consultancy signs set out in writing.
  • Direct advice, including when a smaller package is enough.

We work across all of Dubai. Our office is in Al Quoz.

If you are also planning a three-phase and load upgrade, a DB box and distribution board job, energy audit, lighting design and control or a solar panel installation, we can plan the load, the boards and the drawings together, so the design is done once and priced once.

Our office: Office 1271, Oasis Mall, Al Quoz 1, Dubai, UAE
Phone: +971 55 407 7427
FAQs

Electrical design and estimating questions we hear from Dubai customers

What does an electrical engineer do on a building job?

An electrical engineer works out the load, sizes the supply, boards and cables, draws the single line diagram and schedules, specifies the equipment and checks that the build follows the design. An electrician installs and tests to those drawings. See the electrical engineer section above for the full list.

Do I need an electrical engineer for my villa?

For a new villa that needs a building permit and a supply approval, the drawings go through a registered consultancy. For an extension, a pool, a kitchen or EV charging on an existing villa, a load calculation and a single line diagram are still worth having, because they show whether the board and the supply can take the new load.

What is a single line diagram, and do I need one?

It is one drawing that shows the supply, the boards, the breakers and the cables with their ratings, with one line for the three phases. You need one when you add load, change a board, ask for a supply approval or want an installer to price from a drawing and not from a visit.

How do you calculate the electrical load for a villa?

We list every load, convert the ratings to kVA, apply diversity to each group to get the maximum demand and then find the current at the supply. The worked example above shows the method. The factors come from the rules that apply to your project and not from a guess.

How much does electrical design cost?

It depends on the size of the building, the number of boards, how complete the plans are and which parts of the package you need. A site visit costs AED 50, and the price follows it. We give a fixed price per package after we see the plans, with each part on its own line.

What is a BOQ, and who prepares it?

A BOQ is a list of the items in the design with a quantity and a unit for each. On a large project a cost consultant prepares it. On a smaller one the installer measures from the drawings. We prepare electrical BOQs from our own drawings or from yours.

Can you give me a sample electrical BOQ for a residential house?

The sample in the BOQ section shows the layout, with supply and boards, final circuits, containment, earthing and testing. Its quantities are for an imagined villa. We prepare the real one from your drawings.

Do you do electrical estimating for a house?

Yes. We take the quantities from the drawings, price the materials and the labour, add overhead and profit and give the total with its parts shown. The estimating section shows the steps.

How accurate is an estimate?

An estimate made from complete drawings and a BOQ is more certain than one made from a sketch. We say what the estimate assumes, what it leaves out and what could move the price, so you know the range before you decide.

Can you work from the architect's plans?

Yes. Send them in PDF or CAD with the equipment list and the supply you expect. If the plans change, tell us, because each change reaches the load and the drawings.

Can you check my contractor's quote or drawing?

Yes. We compare the quote with the drawing, check the cable sizes against the breakers, look at the spare capacity and say what is missing or unclear. It is quicker than a new design.

Can you design for a villa that is adding a floor or a pool?

Yes. We visit, read the board, record the breaker ratings and measured loads, and draw what exists and what is proposed. The result shows whether the main supply can take the new load.

Do you submit drawings to DEWA?

Drawings for approval are submitted by a registered consultancy or by a contractor the authority accepts for that purpose. We prepare the information and we install to the approved drawings.

Are you an electrical consultancy?

We are an electrical contractor that prepares design information. Under the rules, practising and advertising as an engineering consultancy needs a trade licence and registration with Dubai Municipality.

Do you give forensic electrical engineer reports?

We do not give expert reports or evidence. We carry out the inspection, testing and thermal imaging that find the cause of a fault, and we fix it.

Can I apply for a job as an electrical engineer with you?

This page is for customers. Send a message on WhatsApp and we will pass it on.

Is there an electrical engineer near me?

Our office is at Office 1271, Oasis Mall, Al Quoz 1, Dubai, and we work across Dubai. Send the plans or photos of the board on WhatsApp, and tell us what you are building or changing. We are available from 9 am to 11 pm, and we answer emergency messages 24 hours a day.

Ready to book electrical design, a BOQ or an estimate?

Send the architect's plans or photos of the board, list the big loads you know about and say what stage the project is at. Tell us whether you want a load calculation, a single line diagram, a BOQ, an estimate or a review of someone else's design. We reply instantly on chat with a view on what you need, what each part involves and a fixed price, so you know what you are buying before any drawing starts.

Electrician in a yellow hard hat with a laptop at a switchgear panel, electrical commissioning check with a laptop in Dubai